The 60L Green Building: |
|
|
|
New Benchmarks, |
|
Old Barriers |
|
|
|
|
|
Perth, 28 September 2001 |
|
|
|
|
|
|
Main Players |
|
Developer
- Green Building Partnership |
|
Architect
- Spowers |
|
Engineering - Lincolne Scott/Advanced |
|
Environmental Concepts |
|
Environmental Adviser |
|
- Sustainable Solutions |
|
Builder
- Hansen Yuncken |
|
|
|
|
|
|
New Benchmarks |
|
|
|
> 65% energy savings |
|
> 90% mains water savings |
|
zero greenhouse footprint |
|
integration of design, environmental management,
behaviour (EMP,lease) |
|
increased occupant productivity (?scale) |
|
|
|
|
|
|
Old Barriers |
|
|
|
Industry specialisation |
|
Lack of questioning/knowledge |
|
Comfort Zoning |
|
Market Irrationality/externalities |
|
Regulatory Framework/Standards |
|
Fear of seeming radical |
|
|
|
|
|
|
Why Bother when so Hard? |
|
|
|
Massive, cost-effective improvements possible
(maybe not where you first think) |
|
Challenging/fun |
|
Someone needs to throw spanner into linear,
stone tablet, Chinese whisper process……. |
|
|
|
|
|
|
Why Bother? (cont.) |
|
|
|
Environmental performance heading south: |
|
- Commercial Sector |
|
- 32Mt CO2 emissions 1990 |
|
(27% from office buildings) |
|
- 63Mt 2010 (BAU) |
|
|
|
Impact on Peak Power Demand (eg, Vic) |
|
|
|
|
|
|
|
|
|
|
|
|
|
The growing interest in ‘green’ development |
|
|
|
Public awareness of the importance of green
building in our society |
|
Market interest in presenting developments as green |
|
Building occupant interest in a more healthy
working environment |
|
Employer interest in increased workplace
productivity |
|
|
|
|
|
|
|
The Commercial advantage |
|
|
|
Savings in energy & water bills |
|
Savings in infrastructure/service costs |
|
Increased worker productivity |
|
Commercial viability |
|
Marketing edge |
|
|
|
|
|
|
|
Driving Environmental Outcomes |
|
|
|
Integrate/synergise design, environmental
management and occupant behaviour |
|
Ambitious goals not incremental improvements |
|
Multidisciplining/workshopping |
|
|
|
|
|
|
|
Environmental Management |
|
|
|
Construction (specifications/EMP) |
|
Building occupation (EMP) |
|
The green lease |
|
|
|
|
|
|
|
|
Green Building Environmental Principles |
|
Minimise resource consumption |
|
Maximise resource reuse |
|
Use renewable or recyclable resources |
|
Protect the natural environment |
|
Create a healthy non-toxic work environment |
|
Pursue quality in creating the built environment |
|
Management of residual materials (waste) |
|
Behaviour patterns & practices |
|
Ecological restoration |
|
|
|
|
|
|
|
Environmental Objectives |
|
Residuals materials management |
|
Water & Wastewater |
|
Energy & Greenhouse gas management |
|
Materials for Construction & Fit-out |
|
Landscaping |
|
Internal Environment quality |
|
Transport |
|
Community impacts |
|
Legal structures |
|
Long-term ecological restoration |
|
Demonstration & educational projects |
|
|
|
|
|
|
The building specification - part 1 |
|
|
|
|
|
Net lettable area 3375 m2 on four
levels |
|
Floor plates of 819, 958, 925 & 675 m2 |
|
Central atrium & lightwells for maximum
daylighting |
|
Natural & active ventilation system with
thermal chimneys |
|
Local tenancy heating & cooling systems |
|
Meeting room (seating 100 people) for use by
tenants & other parties |
|
|
|
|
|
|
|
|
The building specification - part 2 |
|
|
|
|
|
Central
stairs, corner lift |
|
Disabled access at all levels |
|
Rainwater collection |
|
Wastewater treatment |
|
Roof Garden |
|
Bicycle parking |
|
|
|
|
Annual Energy Budget for 60L : |
|
|
|
Expected energy savings over 65 % per year
compared with a conventional office building. |
|
Electrical energy for lighting will be reduced
by over 80%, and for equipment and ventilation, heating & cooling by
over 60%. |
|
Zero fossil fuel-based supply |
|
|
|
|
|
Annual CO2 Emissions for 60L |
|
|
|
Use of
electricity derived from premium non-fossil fuel sources (Green Power) will
enable savings approaching 100 % in annual carbon dioxide emissions,
supplemented by offsite carbon sequestration (even considered offsite
renewable generation) |
|
|
|
|
Annual Water Consumption: |
|
Over 500 kilolitres of rainwater collected in an
average rainfall year for use by taps and showers. |
|
Water efficient fixtures and toilets reduce
water consumption by over 60%. |
|
All wastewater and sewage treated organically on
site and then recycled for toilet flushing and irrigation of the roof
garden. |
|
Total savings in average annual mains water
consumption of over 90% (fire testing) |
|
|
|
|
|
|
|
The 60L competitive advantage : |
|
occupants have some control over their thermal
environment (neighbourliness). |
|
enabling occupants to reduce demand for energy
and water services |
|
enabling occupants to behave in an ecologically
responsible manner. |
|
a pleasant and healthy working environment |
|
significant enhancement of occupant productivity |
|
|
|
|
|
|
Occupant health, comfort and productivity is
achieved through |
|
openable windows |
|
glare-free daylighting |
|
significantly improved internal air quality |
|
materials selected to avoid unwanted volatile
chemical compounds |
|
a landscaped roof garden |
|
occupant control over thermal comfort |
|
|
|
|
|
|
|
60L Building Location3 |
|
|
|
South Carlton, on the northern edge of the
Melbourne CBD. |
|
Close to public transport and the Victoria
Market |
|
In the University of Melbourne – RMIT ‘knowledge’ precinct |
|
Mixed-use, education and research &
development area |
|
|
|
|
|
|
|
Quality environmental management through |
|
|
|
Leases |
|
environmental management systems |
|
user involvement in building operation |
|
creation of a building community |
|
on-line display of building performance |
|
monitoring and fine-tuning of post occupancy
environmental performance. |
|
|
|
|
|
|
Aims of the MCC strategy – |
|
“Environmentally Responsible City” : |
|
|
|
Reduce greenhouse gas emissions |
|
Encourage efficiencies in resource use and reuse |
|
Protect and enhance the City’s biodiversity |
|
improved environmental sustainability of
Council’s policies, services and operations. |
|
|
|
|
|
|
The Regulatory Framework should: |
|
Require the implementation of wholistic ESB
design |
|
Apply to commercial & industrial
developments |
|
Require post-occupancy performance monitoring |
|
Provide protection for existing or approved
buildings with sustainability elements |
|
Prevent overshadowing of solar collection
devices and roof space on adjoining properties |
|
Minimise impacts on passive solar elements of
adjoining buildings |
|
Require building environmental management plans |
|
Set far less wimpish and broader minimum
environmental performance standards |
|
|
|
|
|
|
Take home messages |
|
|
|
Take a wholistic approach to building design,
construction and occupation |
|
Occupant behaviour is as important as bricks
& mortar (given a chance) |
|
Significantly more environmentally sustainable
design of buildings is commercially viable. |
|
ESB principles should be incorporated into the
regulatory and planning systems. ….. |
|
|
|
|
|
|
….Take home messages |
|
|
|
Immediate and life cycle environmental and
financial dividends are available from– energy & water savings AND
occupant productivity |
|
60L provides a raft of demonstrations towards
achieving the triple bottom line in the built environment sector …. And, to
penultimate on something far more important…. |
|
|
|
|
|
Further Information |
|
|
|
www.60Lgreenbuilding.com |
|